Penggunaan Metode Nilai Hasil (Earned Value Analysis) Terhadap Biaya Dan Waktu Pada Proyek Konstruksi Bangunan Perumahan (Studi Kasus Proyek Konstruksi Bangunan Perumahan PT. Graha Praja Kencana Di Desa Ceguk Kecamatan Tlanakan Kabupaten Pamekasan)
Abstract
In a construction project there are various stages related to construction management, in which there are various problems regarding the management of costs and time off work so that in its implementation we need a system for cost management and time management so that in its implementation, the project can be completed on time as planned and the costs incurred according to the needs of the project being worked on. In writing this article the main study is, how is the project performance in terms of cost and time, how is the application of EVA (Earned Value Analysis) to predict the costs and the final time of completion of the project, are there any advantages or disadvantages that may occur in the completion of a construction project PT Graha Praja Kencana Residential Building in Ceguk Village, Tlanakan District, Pamekasan Regency? To answer this problem, a qualitative approach with a descriptive type was conducted. Sources of data obtained through interviews, observations, and documentation with respondents, namely consultants, contractors, and the Director of PT Graha Praja Kencana. From the results of data analysis, it can be concluded that shows that the costs incurred are lower than the planned budget, the time of project implementation according to the schedule from the initial planning, the costs incurred every week from week 1 to week 9 experienced a very significant increase, and the profits obtained by the contractor until the end of the project starting from the first week to the 9th week of Rp. Rp. 8,978,737.20.
References
Ervianto, W. I., 2004. Teori-Aplikasi Manajemen Proyek Konstruksi, Andi, Yogyakarta
Ervianto, W. I, 2005. Manajemen Proyek Konstruksi, Andi, Yogyakarta
Henderson, Kym, 2007. A Breakthrough Extension to Earned Value Management, skripsi, Sydney
Meliasari, Indri & M.Indrayadi, 2011. Earned Value Analysis terhadap biaya dan waktu pada proyek konstruksi, Jurnal Ilmiah, Universitas Tanjungpura
Prastyono, Hendra, G. 2010. Earned Value Analysis Terhadap Waktu Pada Proyek Pembangunan Gedung (Studi Kasus Proyek Pembangunan Gedung C Fakultas MIPA UNS), Surakarta
Priyo, Mandiyo, dkk, 2008. Konsep Earned Value dalam Aplikasi Pengelolaan Proyek Konstruksi (earned value concept for application on construction project management), Jurnal Ilmiah Semesta Teknika Vol 11 No.2 (November, 2008)
Soeharto Imam, 1995. Manajemen Proyek (dari Konseptual Sampai Operasional). Jakarta: Erlangga
Copyright (c) 2020 Dedy Asmaroni, Aldi Setiawan
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (SeeĀ The Effect of Open Access).
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.