The Evaluation of Construction Project Time and Cost Control Using the Earned Value Method (Case Study of Construction of a 200/200 U-Ditch Channel with 10 ton Axle Cover on Jl. Simo Kwagean)

Evaluation of Construction Project Time and Cost Control Using the Earned Value Method (Case Study of Construction of a 200/200 U-Ditch Channel with 10 ton Axle Cover on Jl. Simo Kwagean)

Authors

DOI:

https://doi.org/10.25139/jprs.v9i1.11062

Keywords:

Earned Value Management, Time Control, Cost Control, Construction Project, U-Ditch

Abstract

This study aims to evaluate the time and cost performance of the construction project of U-Ditch 200/200 with a 10-ton axle load cover on Jl. Simo Kwagean, Surabaya, using the Earned Value Management (EVM) method. EVM integrates cost, schedule, and physical progress to measure project efficiency. The data used include the Bill of Quantity (BoQ), project schedule, S-curve, and weekly progress reports. The main indicators analyzed were Planned Value (PV), Earned Value (EV), Actual Cost (AC), Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), and Schedule Performance Index (SPI).

The analysis up to the 10th week shows that CV was positive (IDR 52,575,882 in week 10), indicating cost efficiency, while SV was positive in 7 out of 10 observation weeks, with the highest acceleration of IDR 233,022,814 in week 9. CPI > 1 (1.055) means actual costs were lower than planned, while SPI > 1 (1.47) indicates the project progressed faster than scheduled. The Estimate at Completion (EAC) projection suggests the final cost will be lower than the original budget, and the estimated project duration will be shorter than the contractual schedule.

These results confirm that EVM is effective as an early warning system for monitoring and controlling project time and cost.

References

Annas, F. M., et al. (2025). Evaluasi Kinerja Biaya dan Waktu Pelaksanaan Menggunakan Metode Earned Value (EVM): Studi Kasus Proyek Pengendalian Banjir Kali Lamong. Universitas Muhammadiyah Surakarta.

Hayati, N. I., & Salim, M. A. (2019). Evaluasi Biaya dan Waktu dengan Metode Earned Value Management pada Proyek Masjid AL-Hijri 2. Universitas Ibn Khaldun Bogor.

Junaidi, A., et al. (2022). Kajian Evaluasi Biaya dan Waktu dalam Penanganan Keterlambatan Proyek Menggunakan EVM (Studi Kasus: Jalan Layang Bandara Ahmad Yani). Politeknik Negeri Semarang.

Kurniawan, A. (2017). Analisis Earned Value Waktu dan Biaya Proyek Konstruksi Jalan: Studi Kasus Pelebaran Jalan Simpang Lago - Sorek I. Universitas Islam Riau.

Kurniawan, M. I. (2021). Evaluasi Pengendalian Waktu dan Biaya Proyek Konstruksi Berdasarkan Metode Earned Value dan Crash Project (Studi Kasus pada Proyek Pembangunan SMP Negeri 1 Surabaya). Universitas Narotama..

Kukuh, R. B., et al. (2023). Analisa Pengendalian Waktu dan Biaya pada Proyek Pembangunan Jalan Menggunakan Earned Value Method. Universitas 17 Agustus 1945 Surabaya.

Laia, S., et al. (2024). Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value: Studi Kasus Pembangunan Jalan Deli Serdang. Universitas Pembinaan Masyarakat Indonesia..

Mahapatni, A. R., et al. (2023). Analisis Kinerja Waktu dan Biaya Proyek Pembangunan Jembatan Pangkung Dalem. Universitas Hindu Indonesia.

Ningsi, R., et al. (2022). Pengendalian Waktu dan Biaya dengan Metode EVM pada Proyek Jalan Ruas Kotu - Laba. Universitas Muhammadiyah Parepare.

Priyono, D. (2015). Analisa Kinerja, Biaya, dan Waktu Pelaksanaan Proyek The Samator Surabaya Menggunakan EVM. Institut Teknologi Sepuluh Nopember..

Downloads

Published

2026-03-30

How to Cite

The Evaluation of Construction Project Time and Cost Control Using the Earned Value Method (Case Study of Construction of a 200/200 U-Ditch Channel with 10 ton Axle Cover on Jl. Simo Kwagean): Evaluation of Construction Project Time and Cost Control Using the Earned Value Method (Case Study of Construction of a 200/200 U-Ditch Channel with 10 ton Axle Cover on Jl. Simo Kwagean). (2026). Ge-STRAM: Jurnal Perencanaan Dan Rekayasa Sipil, 9(1), 53–58. https://doi.org/10.25139/jprs.v9i1.11062

Issue

Section

Articles

Most read articles by the same author(s)

Obs.: This plugin requires at least one statistics/report plugin to be enabled. If your statistics plugins provide more than one metric then please also select a main metric on the admin's site settings page and/or on the journal manager's settings pages.